Every remodeler has a story about the change that started as “While you’re here, could you…” and ended in an argument over the final invoice. Often, those arguments aren’t really about the money. They’re about surprise. A clear, prompt, written change order takes the surprise out.
This post covers what to put in your contract before the job starts, what every change order should include, and how to write one so the client says yes. It’s general information, not legal advice. Contract rules vary by state, so check your state’s rules in the license guides and have a local attorney review your contract.
A change order is a written, signed change to the agreed scope, price or schedule after the contract is signed. It can add work, remove work, swap materials or deal with a condition nobody could see at bid time. Once both sides sign it, it becomes part of the contract.
The easiest change orders are the ones your contract already explains. Before the job starts, your contract should say:
Some states write change order rules into law. In Pennsylvania, for example, the Home Improvement Consumer Protection Act says a time-and-materials contract must include an initial cost estimate and state that costs can’t exceed it by more than 10% without a signed, written change order (Act 132 of 2008, as checked on October 16, 2026). Rules like this are why it pays to read your own state’s requirements before you write your contract.
The longer a request sits, the more it turns into an assumption on both sides. Write it up while the conversation is fresh, ideally before you leave the site.
“Add two recessed LED lights over the sink on a new dimmer switch” beats “Add elec per walk.” If the client can’t picture the change, they’ll hesitate to sign it.
Photos of a rotted subfloor do more than any explanation. Show what you found, what happens if it isn’t fixed, and the options.
“Repair the damaged section” and “replace the full subfloor,” each with a price, lets the client choose instead of feeling cornered.
Bundle five changes together and it’s easy for the client to object to all of them over one line. Separate change orders get approved separately.
Use the same markup and labor rate as the original estimate, and include the time it takes to plan, order and supervise the extra work. Credits for removed work should be just as clear.
Walk clients through how changes work when they sign the contract. When the first change order arrives, it’s a process they already agreed to, not a surprise.
Update the schedule, order materials, tell the crew and subs exactly what changed, and bill on the terms you agreed. Keep every signed change order with the contract. At closeout, the final invoice should match the original price plus every approved change order, line by line.
Start with the free change order template, and use the contract template and scope of work template for the clauses that make change orders easier. The glossary defines change orders, allowances and other contract terms. In ECHOPS, change orders go out for e-signature like a quote, approved change orders show up on the crew’s sheet so everyone works from the same scope, and each signed change order bills itself on an invoice of its own.
A change order is a written, signed change to the agreed scope, price or schedule after the contract is signed. It can add work, remove work, swap materials or deal with a hidden condition nobody could see at bid time. Once you and the client both sign it, it becomes part of the contract. The free change order template has the fields to fill in.
It starts in the contract: say that any change to scope, price or schedule needs a signed, written change order before the work starts, who can approve one, how changes are priced and how hidden conditions are handled. Then write each change up the same day, price it the way you priced the job, get both signatures, and update the schedule, the crew, the subs and the next invoice.
As a rule, no. If a client won’t sign, don’t do the changed work. For urgent hidden conditions, like an active leak, protect the home, take photos, tell the client in writing right away and get the change order signed as soon as possible. Some states write change order rules into law, and this isn’t legal advice, so check your state in the license guides.
Yes. Write a $0 change order anyway. It records what changed and that the client agreed, which matters at closeout, when the final invoice should match the original price plus every approved change order, line by line. In ECHOPS, change orders go out for e-signature like a quote, and approved ones show up on the crew’s sheet and each bills itself on an invoice of its own.
Posts are general information, not legal, tax or financial advice.
Keep reading
Pricing, sales, operations and the legal side of contracting.
Read the blog →Starting a remodeling business, selling kitchen and bath jobs, and choosing software.
Read the guides →Estimates, contracts, change orders, invoices and more, as PDF plus Word or Excel.
Get the templates →Try ECHOPS free for 14 days with your own leads and jobs. No credit card, and your workspace is ready in minutes.
Special price: your first 2 months from $49/mo. Limited spots, so sign up today.